Powering Progress: “La Viola” Substation Energized

Powering Progress: “La Viola” Substation Energized

We are proud to announce the successful energization of “La Viola” Substation in Montalto di Castro, located in the province of Viterbo, Italy.

The project underscores our commitment to innovation, sustainability, and excellence in delivering reliable energy solutions.

Thank you to everyone involved in this accomplishment: your dedication makes milestones like this possible!


Un grazie a tutto il nostro team per la partecipazione al Forum Aziendale della scorsa settimana

Un grazie a tutto il nostro team per la partecipazione al Forum Aziendale della scorsa settimana

È stato un momento prezioso di confronto, crescita e condivisione in cui abbiamo avuto l’opportunità di discutere i traguardi raggiunti, i progetti in corso e le sfide future. Abbiamo analizzato l’importanza dell’entusiasmo nel contesto imprenditoriale, offrendo strategie per migliorare la customer experience e favorire l’innovazione all’interno delle imprese. Ogni incontro ci aiuta a fare il punto sulla nostra evoluzione aziendale e ci permette di rafforzare il nostro spirito di squadra.


Another Milestone for Decarbonization

Another Milestone for Decarbonization

We are proud to announce the successful energization of a substation in Sicily serving a Wind Farm.

This marks another important milestone in our journey towards decarbonization and a cleaner, more sustainable future.


We Are Energizing the 220 kV Serre Tavazzano (LO) substation serving a BESS system!

We Are Energizing the 220 kV Serre Tavazzano (LO) substation serving a BESS system!

Stay tuned for more updates as we get closer to completion!


Montalto di Castro (VT) substation energized!

Montalto di Castro (VT) substation energized!

This key milestone reflects our commitment to advancing the energy infrastructure and supporting Italy’s energy transition towards a more sustainable future.


A new milestone achieved!

A new milestone achieved!

We are delighted to share that the Primary Substation in Castegnero has entered the commissioning phase!
This project is a key milestone in our commitment to delivering reliable, efficient, and sustainable energy solutions for our region.
Powering the future, one step at a time!


Rinaldone 150 kV Substation in Province of Viterbo is ready to be energized

Rinaldone 150 kV Substation in Province of Viterbo is ready to be energized

We are powering the future, one project at a time!


The new agrivoltaic plant with a total power of 7 MW in the municipality of Bondeno (FE) is delivering the first kWh of green energy

The new agrivoltaic plant with a total power of 7 MW in the municipality of Bondeno (FE) is delivering the first kWh of green energy

This innovative project combines agriculture and solar energy production, showcasing our commitment to sustainable development and renewable energy. We extended our gratitude to our customer, partners and team members who made this achievement possible.


Il CCI di STE Energy ha pienamente superato i test relativi alla Controllabilità e al Dispacciamento

Il CCI di STE Energy ha pienamente superato i test relativi alla Controllabilità e al Dispacciamento (PF2 e PF3) con il principale DSO italiano.

Ringraziamo Gridspertise per l’elevata professionalità nell’eseguire i test, verificando nel dettaglio tutte le funzionalità richieste (comunicazione, regolazione e cybersecurity), e per averci permesso di partecipare al primo test in Italia sulle PF3 con i requisiti di cyber-security richiesti dalla normativa!

Noi siamo pronti a trasformare tutti gli impianti di produzione in nodi intelligenti della rete elettrica, e voi?